North Stockton HOV Widening

Description: In Stockton, from Charter Way to Hammer Lane. Construct HOV lanes, auxiliary lanes, traffic operations systems, and soundwalls, and rehabilitate/reconstruct pavement.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code
 
Senate District
05
Assembly District 10, 15
Congressional District 11
 
Caltrans District
10
 
 
County/State Route San Joaquin 5
Postmile Begin/End 25 32.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  30302    81,19  
Lane Miles Added (HOV)  8    8  
Lane Miles Added (Mixed)      0  
Peak Period Time Savings (minutes)  559080    296,360  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Sam Sherman (209) 948-7889   sam.sherman@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Sam Sherman (209) 948-7889   sam.sherman@dot.ca.gov
Right of Way Phase
Department of Transportation Sam Sherman (209) 948-7889   sam.sherman@dot.ca.gov
Construction Phase
Department of Transportation Sam Sherman (209) 948-7889   sam.sherman@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$42,470 $0 $42,470
Non-bond Funding
State/Federal*
$32,810 $5,378 $38,188
Local**
$44,220 $3,700 $47,920
Non Budgeted ETC
$0 $0 $0
 
Total**** $119,500 $9,078 $128,578

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$4,000 $0 $4,000 $4,000
Design(PS&E)
$11,180 $0 $11,180 $11,180
Right of Way
$100 $0 $100 $100
Construction
$104,220 $9,078 $113,298 $113,510
 
Total* $119,500 $9,078 $128,578 $128,790

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2007 

02/01/2010 
 

 
04/01/2007 

04/19/2010 
100  04/01/2007 

04/19/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2009 

10/15/2010 
 

 
09/01/2009 

10/15/2010 
100  09/01/2009 

10/18/2010 


Begin Right of Way Phase

End Right of Way Phase
09/01/2009 

07/01/2010 
 

 
09/01/2009 

07/01/2010 
100  09/01/2009 

08/12/2010 


-1 
Begin Construction Phase

End Construction Phase
02/01/2011 

12/30/2014 
 

05/11/2015 
02/01/2011 

12/30/2014 
100  06/02/2011 

01/26/2016 
-4 

-13 
Begin Closeout Phase

End Closeout Phase
01/30/2015 

01/30/2016 
 

 
01/30/2015 

01/30/2016 
100  05/01/2017 

06/29/2020 
-27 

-54 
Corridor System Management Plan
Adoption Date 06/24/2010    06/24/2010   
Implementation Date 06/25/2010    06/25/2010   
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 30302 81,19
Lane Miles Added (HOV) 8 8
Lane Miles Added (Mixed) 0
Peak Period Time Savings (minutes) 559080 296,360

Bond Funding Cost
Adopted:
$42,470,000
Current Approved:
$424,720,000
Actual Expenditures:
$424,200,000

 

Status as of December 31, 2023.